Search This Blog

Tuesday 27 December 2011

Create Work Breakdown Structure (WBS)


Create WBS (Work Breakdown Structure) is the process of subdividing project deliverables and project work into smaller, more manageable components.
The Create WBS process is part of the Project Scope Management knowledge area in the PMP.


Why do project teams need a WBS?
·         Defining and organizing the project work
·         Project budget can be allocated to the top levels of the work breakdown structure
·         Allocating time and cost estimates to WBS, a project schedule and budget can be quickly developed
·         Tracked to identify project performance and identify issues and problem areas
·         Identify potential risks in a given project


PITFALLS:
Lastly let's look at five common pitfalls to creating a WBS. If you can keep these few possible issues in mind when you are creating your WBS, you and your team will be much more successful at creating a useful and accurate Work Breakdown Structure.
1. Level of Work Package Detail
When deciding how specific and detailed to make your work packages, you must be careful to not get too detailed. This will lead to the Project Manager to have to micromanage the project and eventually slow down project progress. On the other hand, work packages whose details are too broad or large become impossible for the Project Manager to manage as a whole.
2. Deliverables--Not Activities or Tasks
The WBS should contain a list of broken down deliverables. In other words, what the customer/stakeholder will get when the project is complete. It is NOT a list of specific activities and tasks used to accomplish the deliverables. How the work is completed (tasks and activities) can vary and change throughout the project, but deliverables cannot without a change request, so you do not want to list activities and tasks in the WBS.
3. WBS is not a Plan or Schedule
The WBS cannot be used as a replacement for the project plan or schedule. A WBS is not required to be created in any type of order or sequence. It is simply a visual breakdown of deliverables.
4. WBS Updates require change control
The WBS is a formal project document, and any changes to it require the use of the project change control process. Any changes to the WBS change the deliverables and, therefore, the scope of the project. This is an important point to help control scope creep.
5. WBS is not an Organizational Hierarchy
The WBS and Organizational Hierarchy chart are never the same thing. Although often similar in appearance, these two documents are very different. The Organizational Hierarchy shows things like chain of command and lines of communication, but the WBS is restricted simply to a project and shows only the deliverables and scope of that project.

The inputs to the WBS are:
1)      Organizational Process Assets – The templates, check list can be find here
2)      Requirements Document – List the functional and non functional requirements of the project
3)      Project Scope Statement – Lists what needs to accomplished in this project
Tools and Techniques:
Decomposition is the sub division of project deliverables into smaller components, until the work and deliverables are broken down as work packages.
This WBS breaks the project work down by phases.
The phases are break down by deliverables.
The planned work contained within the lowest level of WBS components is called as work packages.
The work packages can be scheduled, assigned to resources, cost estimated, monitored and controlled.

How to decompose the deliverables into the work package:
·         Start with a major deliverables
·         Identify the related works in the deliverables
·         Structure and organize the deliverables
·         Begin breaking down the project into smaller and smaller pieces
·         Developing and assigning the identification codes to the WBS work packages
·         Verify the work package is assigned and manageable
The good WBS should have:
·         Easy to understand
·         Corresponds to job description
·         Not too detailed
·         Preserve the most important relationship among the tasks
·         Doesn’t add length to the project
The outputs are:
1) WBS:
WBS is all about taking deliverables and coming up with work packages that will create them.
The sample WEBS contains:
·         Task ID
·         Task Description
·         Predecessor
·         Owner
·         Role
·         % Complete
·         Start Date
·         Finish Date
·         Deliver To
Tools to create WBS:
·         Mind Mapping Software
·         Microsoft Project Planner
·         I-Planner
·         Excel Sheet

2) WBS Dictionary:

The WBS dictionary is the document that supports WBS which provides more detailed description of the components in the WBS.
The WBS dictionary document contains:
·         Work package id
·         Work package name
·         Responsible person
·         Schedule milestone
·         Associated activities
·         Cost estimate
·         Quality requirements
·         Acceptance criteria
·         Technical information

3) Scope Baseline:
As the project goes on, you will want to compare how you are doing to what you planned for. So, the scope baseline is there to compare against. It’s made up of the scope statement, the WBS, and the WBS Dictionary. When work gets added to the scope through change control, you need to change the baseline to include the new work packages for that work, so you can always track yourself against the plan.


4) Project document updates:
Whenever a change is approved through change control, the baseline needs to be updated. Approved changes are changes to the scope management plan also, so it’s important that you re-baseline your project when they are approved. That way, you’ll always be comparing your performance to the most updated plan.


PITFALLS:
Lastly let's look at five common pitfalls to creating a WBS. If you can keep these few possible issues in mind when you are creating your WBS, you and your team will be much more successful at creating a useful and accurate Work Breakdown Structure.
1. Level of Work Package Detail
When deciding how specific and detailed to make your work packages, you must be careful to not get too detailed. This will lead to the Project Manager to have to micromanage the project and eventually slow down project progress. On the other hand, work packages whose details are too broad or large become impossible for the Project Manager to manage as a whole.
2. Deliverables--Not Activities or Tasks
The WBS should contain a list of broken down deliverables. In other words, what the customer/stakeholder will get when the project is complete. It is NOT a list of specific activities and tasks used to accomplish the deliverables. How the work is completed (tasks and activities) can vary and change throughout the project, but deliverables cannot without a change request, so you do not want to list activities and tasks in the WBS.
3. WBS is not a Plan or Schedule
The WBS cannot be used as a replacement for the project plan or schedule. A WBS is not required to be created in any type of order or sequence. It is simply a visual breakdown of deliverables.
4. WBS Updates require change control
The WBS is a formal project document, and any changes to it require the use of the project change control process. Any changes to the WBS change the deliverables and, therefore, the scope of the project. This is an important point to help control scope creep.
5. WBS is not an Organizational Hierarchy
The WBS and Organizational Hierarchy chart are never the same thing. Although often similar in appearance, these two documents are very different. The Organizational Hierarchy shows things like chain of command and lines of communication, but the WBS is restricted simply to a project and shows only the deliverables and scope of that project.

23 comments:

  1. Great information.Thanks for sharing this useful information about Work Breakdown Structure

    ReplyDelete
  2. This comment has been removed by the author.

    ReplyDelete
  3. Hi,

    Great post of Work Breakdown Structurefrom PMP

    ReplyDelete
  4. Sir, your articles are very nice.. kindly give us an detailed view of a project starting from Requirement gathering to Support.. It will be very useful for us...

    ReplyDelete
  5. Awesome! Education is the extreme motivation that open the new doors of data and material. So we always need to study around the things and the new part of educations with that we are not mindful.
    java training in marathahalli | java training in btm layout

    java training in jayanagar | java training in electronic city

    java training in chennai | java training in USA

    selenium training in chennai

    ReplyDelete
  6. I am definitely enjoying your website. You definitely have some great insight and great stories. 
    python training in tambaram
    python training in annanagar
    python training in OMR
    python training in chennai

    ReplyDelete
  7. Thanks for splitting your comprehension with us. It’s really useful to me & I hope it helps the people who in need of this vital information.
    Blueprism online training

    Blue Prism Training in Pune

    Blueprism training in tambaram

    ReplyDelete
  8. I am really happy with your blog because your article is very unique and powerful for new reader.
    Click here:
    selenium training in chennai
    selenium training in bangalore
    selenium training in Pune
    selenium training in pune
    Selenium Online Training

    https://scala-bility.blogspot.com/2015/05/scalajs-and-react-building-application.html

    ReplyDelete
  9. It is a great post. Keep sharing such kind of useful information.

    Article submission sites
    Education

    ReplyDelete

  10. You provided a nice post for business intelligence business analyst online course

    ReplyDelete
  11. It is a known fact that ILLUMINATI consist of Multi Millionaires,Billionaires who have major influence regarding global affairs, and planning of a New world order. Many world leaders, Presidents, prime ministers, royalty and senior executives are members of ILLUMINATI. follow the steps to Excel in Life. you'll have numerous benefits,for the FIRST TIME IN HISTORY, we are opening our doors to those who believe. If you would like to join ILLUMINATI , to sign up Text: leovincey08@gmail.com or whatsapp +2349033667873 now if you are really serious to help your self

    ReplyDelete
  12. Hey! Amazing work. If you are searching for genuine Quickbooks Customer Service dial Quickbooks Customer Support Number 1-855-756-1077 for immediate help.

    ReplyDelete
  13. wonderful article contains lot of valuable information. Very interesting to read this article.I would like to thank you for the efforts you had made for writing this awesome article. Primavera p6 Training Online | Primavera Training Chennai

    ReplyDelete
  14. Techforce services is a Salesforce Consulting Services in Australia Specialising in delivering end to end Salesforce solutions ,Consulting, Implementation DevOps partners in australia We deliver applications and services more rapidly and reliably, but it’s more than a methodology – it cuts to the very core.Salesforce Data Analytics let us help you become a data driven organisation and ensure your data is working hard for your business This includes implementi
    Techforce services in Australia
    Salesforce Consulting Services in Australia
    Salesforce Staff Augmentation in Australia
    Salesforce Data Analytics
    DevOps Partners in Australia
    Managed Projects Salesforce Australia

    ReplyDelete
  15. It is very interesting! Really useful for me and thank you for this amazing blog.
    VA Divorce Lawyers
    How to get a Divorce in VA

    ReplyDelete
  16. It is very useful for me and thank you so much for your sharing this post. Keep updating...
    Separation Before Divorce
    Cost of Legal Separation VS Divorce
    Online Solicitation Of A Minor

    ReplyDelete