Scrum
|
Extreme Programming
|
Scrum's main goal is to get estimations of how long development will
take.
|
XP is more about helping developers get things done as quickly and maintainable
as possible.
|
Team typically works in iterations (called sprints) that are from two
weeks to one month long.
|
Team typically works in iterations that are one or two weeks long.
|
Scrum teams do not allow changes into their sprints.
|
XP teams are much more agreeable to change within their
iterations.
|
Product owner prioritizes the product backlog but the team determines
the sequence in which they will develop the backlog items
|
Work in a strict priority order which is set by Product Owner
|
Scrum provides agile management mechanisms and doesn’t prescribe any engineering
practices
|
XP prescribes engineering practices like test-driven development, the
focus on automated testing, pair programming, simple design, refactoring, and
so on.
|
SCRUM places great responsibility in the Scrum Master, who manages
the development team.
|
In XP, the practice of collective ownership allows any programmer to
modify a section of code when it needs to be fixed.
|
XP requires that the software be validated at all times, to the
extent that tests are written prior to the actual software.
|
In SCRUM, validation of the software is completed at the end of each
Sprint during the Sprint Review, not at each step within the Sprint.
|
Search This Blog
Thursday, 7 February 2013
Difference between Scrum and Extreme Programming
Sunday, 13 January 2013
How to manage the project without project manager?
There are few points forced to manage the project without Project Manager:
- Project is small in terms of quantity of work and number of people to carry out that work
- The complexity and risk is low
- The sponsor feels that they do more on technical jobs or R&D or performing case study, so that the need of the project management is minimal (this point is opposite to the above points as the technical jobs, R&D and case study have more uncertainties and challenges)
- No budget to cover the cost of Project Management indeed Project Manager
Wednesday, 9 January 2013
Estimate the agile project's budget using story points
The budget of the project calculated mostly based on the
effort. In agile projects the budget can be calculated based on story point
also. The project manger needs to have clear input on the velocity of the team
to calculate the budget.
Assume you have team size of 8 with the rate of 80$ per hour.
The total working hours spent by person per week is 40 hours.
Total cost per week = 8 (team size) * 80 (rate in $) * 40 (hours/week) = 25,600$
Assume based on the velocity, you team able to complete 16 user stories.
Cost per story point = 25,600 (Cost of resources based on the effort spent) / 16 (Story points per week)
= 1,600 $
Assume you have 500 story points planned for the project.
Project Budget = 1,600 * 500 = 8,00,000 $
Project Budget = Cost
per Story Point * Total Story Points
Cost per story point = Cost of resources based on the effort
spent / Story points per weekAssume you have team size of 8 with the rate of 80$ per hour.
The total working hours spent by person per week is 40 hours.
Total cost per week = 8 (team size) * 80 (rate in $) * 40 (hours/week) = 25,600$
Assume based on the velocity, you team able to complete 16 user stories.
Cost per story point = 25,600 (Cost of resources based on the effort spent) / 16 (Story points per week)
= 1,600 $
Assume you have 500 story points planned for the project.
Project Budget = 1,600 * 500 = 8,00,000 $
Wednesday, 2 January 2013
What’s New in PMBOK Guide, 5th Edition
Are you ready for the newest guide to the Project Management
Body of Knowledge? PMI is poised to release the new version of the PMBOK Guide
before the end of 2012.
I have highlighted what’s new in PMBOK5 compare with PMBOK4
below: Total numbers of process in PMBOK4 are 42.
Total numbers of process in PMBOK5 are 47, the Project Stakeholder Management knowledge area has been added newly.
Thursday, 27 December 2012
How to monitor and control projects
Monitoring and Controlling is the largest and continuous
part of the project management. It keeps eye on everything that’s happing in/out
of the project and adjusts as needed.
A good project manager is constantly monitoring every single thing happing in the project. If you find the problem latter it’s hard and more expensive to solve it.
The below practices need to be followed by a project manager for an effective monitor and control of the project:
A good project manager is constantly monitoring every single thing happing in the project. If you find the problem latter it’s hard and more expensive to solve it.
The below practices need to be followed by a project manager for an effective monitor and control of the project: